Migrating a Travel Group from MYOB to Microsoft Dynamics 365 Business Central

Quick answer

NexusWorks implemented Microsoft Dynamics 365 Business Central for a travel business replacing MYOB. Business Central went live on June 15, 2026 for new-system bookings, ran in parallel with MYOB to the September 30 year end, and took full cutover on October 1, 2026 with MYOB closing balances migrated.

At a glance

Client
Travel business within a larger travel group
From / to
MYOB to Microsoft Dynamics 365 Business Central
Fiscal year end
September 30
Timeline
Go-live June 15, 2026; parallel run to September 30; full cutover October 1, 2026
Integrations
New reservation system feeding Business Central; legacy reservation system retired

01

The challenge

The business was changing its accounting system and its reservation system at the same time. Finance needed GL mapping, balance sheet, profit and loss and trial balance reports from day one, but MYOB still had to run the old reservation flow until year end without double counting.

02

Our approach

  1. Cutover design. Business Central took only bookings from the new reservation system during the parallel run, while MYOB kept legacy bookings and other transactions.
  2. Configuration. Company partitions, chart of accounts mapping, dimensions and posting groups were configured from a checklist agreed with finance.
  3. Integration mapping. We documented how reservation bookings flowed into MYOB and rebuilt that flow in Business Central.
  4. Reporting from day one. GL code mapping and trial balance, balance sheet and P&L exports were built to the finance team's specification.
  5. Year-end cutover. MYOB closing balances at September 30 were migrated as Business Central opening balances, then MYOB was decommissioned.

03

Results delivered

  • Business Central live on schedule with a controlled parallel run.
  • Year-end cutover aligned to the September 30 fiscal year end.
  • Finance reports available in Business Central from go-live.
  • Legacy system retired with a clean opening trial balance.

04

Frequently asked questions

For a small to mid-sized business, typically three to six months, depending on integrations, data migration and whether a parallel run is used.

Related services

ERP ConsultingDynamics 365 Business CentralFractional CFO →

Key terms See the glossary →

Microsoft Dynamics 365 Business Centralconfiguration packageschart of accounts mappingdimensionsposting groupspartitioned companiesparallel runcutoverclosing trial balance migrationreservation system integrationGL code mapping
Reviewed by a California-licensed CPANexusWorks LLC · Last updated Oct 17, 2026

Facing a similar situation?

Book a discovery call with our CPA team